Monday, October 29, 2018: As a follow up to the just concluded donors’ coordination meeting in Conakry, Republic of Guinea, the General Manager of TRANSCO CLSG met with EPC contractors implementing the CLSG project at the Headquarters in Abidjan on Monday, October 29, 2018.
The objective of the meeting was to reemphasize meeting delivery deadline of the project by 2019. The General Manager, Mohammed M. Sherif urged the EPC contractors to keep the project implementation on track. At the end of the meeting, an aide-mémoire containing action plans was signed between TRANSCO CLSG and EPC contractors.
The CLSG project Owner’s Engineer, TRACTEBEL also attended the one-on-one meeting.
Talking points included:
- Presentation of the commissioning projection of the CLSG Project and the reason to reduce the implementation time frame of the Lot (by TRANSCO CLSG);
- Presentation of a new strategy of implementation (additional teams/equipment/ etc…) and proposal of a revised time schedule to deliver the project by December 2019
- Status of identification of final locations of Substation