Pre-Testing at Kenema Substation complete

Read more

PROJECT UPDATE

Kenema substation:

Pre-commissioning tests completed for primary equipment; disconnectors, circuit breakers, instrument transformers, surge arresters, power transformers etc…and tests nearly completed for secondary equipment; relay and protection tests, electrical interlock, SCADA list, injection current and voltage, battery charging and discharging etc…

The CLSG interconnection project remains on course!

SEE PICTURES FROM FRANCIS VANDY