UPDATES
MORE PROGRESS: EPC contractor, Sieyuan and its subcontractor have started mobilizing on the Yekepa Substation (YSS) project site in Nimba County. First heavy-duty equipment has arrived and bush clearing ongoing. Earthworks are in progress for the preparation of YSS construction site.
The clearing of the Mano Substation Site is in progress in Grand Cape Mount County.
- March 2018 – Extensive progress made in CLSG project implementation
- January 2018 – Equipment for CLSG Project arrive in Liberia
- August 2017 – LIDAR Survey underway in Liberia