The kick-off meeting of the contract for the Owners’ Engineer Phase 2 is scheduled for January 24 and 25, 2017 at the TRANSCO CLSG Country Office in Freetown, Sierra Leone.
The kick-off meetings of the first four transmission line Lots have been scheduled as follows:
Kick-off meeting Owner’s Engineer Phase 2 | TRACTEBEL BELGIUM | 24/01-25/01/17 | TRANSCO CLSG/ Sierra Leone Office |
Kick-off meeting – TL WB-EIB 04/ Lot 3 | JOYTI STRUCTURES LTD | 26/01/2017 | TRANSCO CLSG/ Sierra Leone Office |
Kick-off meeting -TL WB-EIB 04/ Lot 4 | KALPATARU | 27/01/2017 | TRANSCO CLSG/ Sierra Leone Office |
Kick-off meeting -TL WB-EIB 04/ Lot 2 | NCC | 30/01/2017 | TRANSCO CLSG/ Liberia Office |
Kick-off meeting – TL WB-EIB 04/ Lot 1 | JV ELECNOR EIFFAGE | 31/01/2017 | TRANSCO CLSG/ Liberia Office |