The testing and installation of Power Transformers have been completed for Kenema substation in Sierra Leone. Installation of control panels and cable terminations remains in progress.
Primary Equipment (circuit breakers, instrument transformers, disconnectors, surge arresters etc) has been installed while testing of this equipment is in progress.
SEE PHOTOS by Fransic Vandy, Engineering and contract specialist, Sierra Leone
Workshop and warehouse construction is at 90% and crane installation has been completed. Civil works for control building, residential and guest buildings almost completed.
The CLSG interconnection continues to score more milestones.