Sidiki TRAWALLY

“The people are impatient,” Gen. Keita

Governor of Nzerekore Gen. Mohamed Lamine Keita addresses the TRANSCO-GridCo team   Sustainable electricity supply will have a massive impact on Nzerekore and its surrounding region, says the newly appointed Governor of Nzerekore, General Mohamed Lamine Keita. Gen. Keita told the visiting TRANSCO CLSG and GridCo delegations during a courtesy …

Read More »

GridCo tours TRANSCO CLSG facilities

TRANSCO CLSG GM Sherif (l) with Amb. Blay-Amihere A six-member high-powered Executive team from the Ghanian based energy company, GridCo, including its Chairman of the Board, Amb. Kabral Blay-Amihere is on a week-long working visit with TRANSCO CLSG to assess the CLSG project infrastructure in Liberia, Sierra Leone and Guinea. The group …

Read More »

Kenema Substation Energized

The energized Kenema substation STRONG PROGRESS!! The sequential energization of the 225kV CLSG Transmission Line and substations continues! The CLSG project has achieved another major milestone – the energization of the Kenema Substation. TRANSCO CLSG has successfully energized the 225/66/33 kV substation in Kenema district, Sierra Leone. This milestone will …

Read More »

TRANSCO CLSG seeks contract extension with CIE

TRANSCO CLSG is holding discussions with the CIE, an Ivorian company responsible for Operation and Maintenance services of the CLSG transmission line and substations in Cote d’Ivoire and Liberia to agree a contract extension of its services beyond August 2021. TRANSCO CLSG signed a temporary Operations and Maintenance (O&M) contract …

Read More »

Nzerekore substation making progress

The Control Room at Nzerekore substation The transmission line section from Yekepa to Nzerekore is about 95% complete. The construction of the Nzerekore substation is making strong progress. The substation is expected to be completed by December 2021. See Photos from Germain Paye, TRANSCO CLSG’s Social Safeguard Assistant. Previous story …

Read More »

GM: Overall progress of the project is 93%

General Manager Sherif addresses the 25th Board meeting in Abidjan In his report to the Board of Directors of TRANSCO CLSG at its 25th seating, General Manager Mohammed Sherif disclosed that despite the challenges in the project implementation, particularly the Covid-19 pandemic, the CLSG project achieved major milestones. Mr. Sherif …

Read More »